Sprint burndown charts – what do they measure

Posted by:

|

On:

|

, ,

Sprint Burndown Charts are visual tools used in Agile and Scrum to track the progress of work in a sprint (a time-boxed iteration). They plot the amount of work remaining to be completed on the vertical axis and the time on the horizontal axis. As the sprint progresses, the chart is updated automatically to reflect the actual work completed. Sprint burndown charts are easily generated using an online tool such as Jira, Rally, smartsheets, Version One, TFS, Salesforce Agile Accelerator.

Why They Are Useful:

  1. Progress Tracking: Sprint Burndown Charts provide a clear, visual representation of how much work remains, allowing teams to track progress in real-time.
  2. Early Problem Identification: They help identify issues or bottlenecks during the sprint. If the burndown line deviates from the ideal trajectory, it signals potential problems.
  3. Scope Management: Burndown Charts assist in scope management. If the remaining work exceeds the available time, teams can adjust priorities or take action to stay on track.
  4. Communication: They facilitate transparent communication within the team and with stakeholders, ensuring everyone is aware of the sprint’s status.

How to Read and Identify Trends:

  • Ideal Line: This represents the ideal rate at which work should be completed for a successful sprint. It’s a straight line from the starting point to zero at the end of the sprint.
  • Actual Line: The actual work remaining is plotted each day. If the actual line is consistently below the ideal line, it indicates the team is ahead of schedule. If above, they are falling behind.
  • Trends: Trends can be identified by looking at the shape of the actual line over time. It’s important to consider the team’s daily progress. For example, if the line initially slopes downward but then starts to increase, it suggests a slowdown.
  • Variance: The gap between the ideal and actual line indicates the variance. A consistent gap may suggest the team’s velocity and predictability.

Sprint Burndown Charts are a valuable tool for Agile teams to ensure they are on track to meet their sprint goals. By regularly reviewing the chart, teams can make data-driven decisions, adapt to changes, and maintain focus on the most important work items.